Glenview Park
Working to replace stolen plants, and looking into installing fencing to prevent plants from being trampled on
Almaden Meadows
Irrigation has been fixed, so watering should be back on track
Conservation group came and did a major clean up.
Parking lot at Los Alamitos Creek Trial
Striping completed, and project is done
Removed a bunch of overgrowth of weeds and poison oak from the equestrian trail
Albertson Parkway
5 bio-retention areas, in progress of being maintained.
Cathedral Oaks Park
Conservation group came to clean up
Cahalan Park
Concrete Repaired
Carrabelle Park
Rodent Abatement in beginning of September
Guadalupe Oak Grove Park
Finding way to bring in erosion control before rainy season to protect trails
Foothill Park
Looking for retaining wall or some other method to shore up Foothill Park
Jeffrey Fontana Park
Fencing around new sod is still up to resolve a grub problem that has developed in the grass.
Rodent abatement is pending, if not already in progress
T.J. Martin
Rodent abatement is pending, if not already in progress
Concrete Repaired
George Page Park
Abatement of various rodents in the park
Releveled the dirt to fill in holes to receed the whole area
Fencing around the area while seed takes hold
La Colina Park
Clean up of weeds, trimming trees all around perimeter of fences
Foothill Park
Planting pollinator plants around the bottom of the park
Target is Early December
Chris Hotts Park Renovation
Status: